Building Project Schedule

        

Hannibal Central School District
Additions & Alterations

Dates (Revised 4/8/02)
1.   Sitework Phase 1 Start

2.   SED Submission OK

3.   Out to Bidders

4.   Recommence Sitework 

5.   Bids Received

6.   Begin Fairley CR Addition

7.   Begin Mech/Elec Alterations

8.   Begin Kenney CR Addition

9.   Begin Kenney Gym Addition

10. Begin Library Additions

11. Begin Major Interior Additions

12. Completion of CR Additions

13. Occupy Kenney Gym Addition

14. Complete All Alterations

 
October 7, 2001

February 1, 2002

April 1, 2002

April 15, 2002

May 6, 2002

May 13, 2002

May 13, 2002

May 13, 2002

October 14, 2002

April 18, 2003

July 1, 2003

July 25, 2003

October 3, 2003

October 31, 2003

   

 