nDMK
Alterations
Continuation of
electric rough-ins, including energizing the new switchgear and main
distribution panel.
The existing electric
system will be gradually replaced with new.
nNew
plumbing service entrance including new meter, backflow preventors
installed.
nContinuation
of rough-ins for new HVAC and Plumbing mains and feeders.
DMK Additions
nStructural
steel, floor slab, decks and roof completed at Classroom Addition.
Completion of
formwork, footers, walls and interior piers for the Gym Addition by
end of this month.
nMasonry
exterior walls may begin at the Classroom Addition most likely after
floor slabs are completed.
DMK Sitework
nComplete
all change order work to improve drainage and expand fields and
green spaces.
Fairley
Alterations
nComplete
ceramic tile work on corridor side of new Speech and Psychology
Rooms.
nContinuation
of electrical rough-ins, including energizing the new switchgear
and main distribution panel.
nWork
on new gas piping on roof and in mechanical spaces.
nContinuation
of rough-ins for new HVAC and Plumbing mains and feeders.
Fairley
Additions
nCompletion
of all foundation walls and piers including reinforcing, CIP
concrete placement, anchor bolts and leveling plates.
nBegin
installation of Classroom and Gym Addition structural steel
starting at the north side.
nPour
slab-on-grade and second floor deck.
Fairley
Sitework
Demobilized
until Spring 2003.